The purpose of this blog is to keep employees informed about the progress of the new KUB Engineering Building, whichwill be constructed on the north side of the E&O Building on the Hoskins Center Campus.
Please contact David Keck (X2220) or Randy O'Neal (X7236) with questions.
Featured Post
Jan 26, 2018
January 19, 2018 UPDATE
Electric Vehicle Charging Stations (Schedule Update) – In preparation for demolition of the E&O Building Covered North Parking Lot, Properties will relocate the four Electric Vehicle Charging Stations to the north end of the East Parking Lot (near the Ed Shouse Gate). This work has been rescheduled for the week of January 22.
Communications Line Installation – Contractor Service One and its boring subcontractor continue work on installation of the new communications line serving the E&O Building. Crews and related construction equipment will maintain a presence in the West Parking Lot and the access road near the main entrance through early February. E&O Building employees may notice elevated noise levels as the contractor drills for conduit installation in the basement area.
South Parking Lot Extension – Contractor Southern Constructors, Inc. (SCI), began excavating for the project to add 84 parking spaces and a landscaped area for stormwater management adjacent to the South Parking Lot. Construction of the new parking lot is expected to last from early January through late winter. As a reminder, SCI has blocked off the last row of parking spaces and the southwest corner of the lot. The walking trail between the South Parking Lot and the Mechanical Building will be closed during construction (see map on KUB monitors).
Communications Line Installation – Contractor Service One and its boring subcontractor continue work on installation of the new communications line serving the E&O Building. Crews and related construction equipment will maintain a presence in the West Parking Lot and the access road near the main entrance through early February. E&O Building employees may notice elevated noise levels as the contractor drills for conduit installation in the basement area.
Subscribe to:
Posts (Atom)
-
Contractor crews will be performing potholing work to locate existing undergound utilities in the roadway area in front of the E&O Build...
-
Beginning this week and lasting through April 2018, the E&O Building South Parking Lot (Area 1) is being extended to add 84 spaces to o...
-
Electric Vehicle Charging Stations (Schedule Update) – In preparation for demolition of the E&O Building Covered North Parking Lot, Prop...